Analisis Efisiensi Biaya Bahan Baku Semen OPC Menggunakan Metode Material Requirement Planning Lot for Lot (MRP-LFL) dan Just in Time (JIT) pada PT ABC
DOI:
https://doi.org/10.56211/blendsains.v5i1.1713Keywords:
Beton Pracetak; Efisiensi Biaya; Just in Time; MRP-LFL; Semen OPC
Abstract
Penelitian ini bertujuan menganalisis efisiensi biaya pengadaan bahan baku semen OPC (Ordinary Portland Cement) pada PT ABC, perusahaan manufaktur beton pracetak di Karawang. Penelitian membandingkan sistem pengadaan eksisting dengan Material Requirement Planning berteknik Lot for Lot (MRP-LFL) dan Just in Time (JIT). Data sekunder dari Departemen Perencanaan dan Evaluasi Produksi selama April 2025 meliputi kebutuhan harian, volume pemesanan, tanggal kedatangan, lead time, dan sisa stok. Hasil analisis menunjukkan bahwa MRP-LFL mampu menekan sisa stok akhir dari 30.025 kg menjadi 0 kg. Simulasi JIT menurunkan biaya penyimpanan dari Rp2.400.000 menjadi Rp300.000 per bulan, sehingga menghasilkan penghematan Rp2.100.000 atau 87,5%. Temuan ini menunjukkan bahwa MRP-LFL efektif untuk menyelaraskan kuantitas pemesanan dengan kebutuhan aktual, sedangkan JIT memperkuat efisiensi biaya melalui pengadaan tepat waktu. Integrasi keduanya direkomendasikan dengan dukungan keandalan pemasok, pengendalian lead time, dan sistem informasi persediaan yang terintegrasi.
Downloads
References
[1] R. Lara, “Analisis Sistem Akuntansi dalam Pengendalian Persediaan Barang Dagang pada CV. Tekno Komputer,” Eklektik J. Pendidik. Ekon. dan Kewirausahaan, vol. 3, no. 2, pp. 125–133, 2020, doi: 10.24014/ekl.v3i2.25428.
[2] E. P. Lahu and J. S. B. Sumarauw, “Analisis Pengendalian Persediaan Bahan Baku Guna Meminimalkan Biaya Persediaan pada Dunkin Donuts Manado,” J. EMBA J. Ris. Ekon. Manajemen, Bisnis dan Akunt., vol. 5, no. 3, pp. 4175–4184, 2017, doi: 10.35794/emba.5.3.2017.18394.
[3] S. Dwiningsih and A. A. Pratama, “Penerapan Metode Just in Time sebagai Alternatif Pengendalian Persediaan Bahan Baku pada PT Behaestex, Pandaan Pasuruan,” J. Apl. Manaj. dan Inov. Bisnis, vol. 4, no. 1, pp. 58–70, 2021, doi: 10.47201/jamin.v4i1.105.
[4] M. A. Daroini and A. F. I. Himawan, “Analisis Pengendalian Persediaan Bahan Baku Songkok ZNR dengan Menggunakan Metode Material Requirement Planning (MRP),” J. Mhs. Manaj., vol. 2, no. 02, pp. 155–166, 2022, doi: 10.30587/mahasiswamanajemen.v2i02.3035.
[5] P. D. Septyawati, “Pengelolaan Bahan Baku Kertas Produksi Kemasan Berbasis Material Requirement Planning,” 2022.
[6] Z. Fahrudin, A. Widayanti, and I. Yuniar, “Aplikasi Manajemen Persediaan Bahan Baku Mempertimbangkan Unit Diskon dan Kapasitas Gudang dengan Metode Lot for Lot (Studi Kasus: Bangnana Chips, Bandung),” eProceedings Appl. Sci., vol. 5, no. 3, 2019.
[7] L. Maduma and Sriyanto, “Usulan Perencanaan Kebutuhan Bahan Baku Readymix dengan Metode Material Requirement Planning (MRP) pada Batching Plant Lampung PT Waskita Beton Precast, Tbk untuk Proyek Tol Trans Sumatera,” Ind. Eng. Online J., vol. 8, no. 3, 2019, [Online]. Available: https://ejournal3.undip.ac.id/index.php/ieoj/article/view/24305
[8] M. I. Qureshi, M. Iftikhar, M. N. Bhatti, T. Shams, and K. Zaman, “Critical Elements in Implementations of Just-in-Time Management: Empirical Study of Cement Industry in Pakistan,” Springerplus, vol. 2, p. 645, 2013, doi: 10.1186/2193-1801-2-645.
[9] X. Zhao and K. Lam, “Lot-sizing Rules and Freezing the Master Production Schedule in Material Requirements Planning Systems,” Int. J. Prod. Econ., vol. 53, no. 3, pp. 281–305, 1997, doi: 10.1016/S0925-5273(97)00111-4.
[10] G. Singh and I. S. Ahuja, “An Evaluation of Just in Time (JIT) Implementation on Manufacturing Performance in Indian Industry,” J. Asia Bus. Stud., vol. 8, no. 3, pp. 278–294, 2014, doi: 10.1108/JABS-09-2013-0051.
[11] T.-D. Phan and N. Athigakunagorn, “Discrete-event Simulation-based Decision Making of Just-In-Time Strategies for Precast Concrete Supply Chain Using Batch Delivery and Offsite Inventory Level,” Uncertain Supply Chain Manag., vol. 10, no. 3, pp. 679–692, 2022, doi: 10.5267/j.uscm.2022.5.007.
[12] W. A. Andriyanto, G. H. G. Senoaji, and N. D. Cahyani, “Inventory Management in Precast Concrete Industry: A Strategic Study of Raw Material Management,” Maj. Ekon., vol. 31, no. 1, pp. 73–89, 2025, doi: 10.36456/majeko.vol31.no1.a10220.
[13] B. Zhu, Y. Zhang, K. Ding, F. T. S. Chan, J. Hui, and F. Zhang, “Lot-sizing Decisions for Material Requirements Planning with Hybrid Uncertainties in a Smart Factory,” Adv. Eng. Informatics, vol. 51, p. 101527, 2022, doi: 10.1016/j.aei.2022.101527.
[14] J. F. Kros, M. Falasca, and S. S. Nadler, “Impact of Just-in-Time Inventory Systems on OEM Suppliers,” Ind. Manag. Data Syst., vol. 106, no. 2, pp. 224–241, 2006, doi: 10.1108/02635570610649871.
[15] J.-S. Yang and J. C.-H. Pan, “Just-in-Time Purchasing: An Integrated Inventory Model Involving Deterministic Variable Lead Time and Quality Improvement Investment,” Int. J. Prod. Res., vol. 42, no. 5, pp. 853–863, 2004, doi: 10.1080/00207540310001632448.
Downloads
Article History
Pages: 299-306
How to Cite
Issue
Section
License
Copyright (c) 2026 Thomas Wu, Bayu Adzikri Ramadhan

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Penulis yang mempublikasikan naskahnya pada Blend Sains Jurnal Teknik menyetujui ketentuan berikut:
Hak cipta atas artikel apapun dalam Blend Sains Jurnal Teknik dipegang penuh oleh penulisnya di bawah lisensi Creative Commons Attribution-ShareAlike 4.0 International License. dengan beberapa ketentuan sebagai berikut:
"Penulis mengakui bahwa Blend Sains Jurnal Teknik berhak sebagai yang mempublikasikan pertama kali dengan lisensi Creative Commons Attribution-ShareAlike 4.0 International License / CC BY SA 4.0"
"Penulis dapat memasukan tulisan secara terpisah, mengatur distribusi non-ekskulif dari naskah yang telah terbit di jurnal ini ke dalam versi yang lain (misal: dikirim ke respository institusi penulis, publikasi ke dalam buku, dll), dengan mengakui bahwa naskah telah terbit pertama kali pada Blend Sains Jurnal Teknik."
"Pembaca diperbolehkan mengunduh, menggunakan, dan mengadopsi isi artikel selama mengutip artikel dengan menyebutkan judul, penulis, dan nama jurnal ini. Pengutipan tersebut dilakukan demi kemajuan ilmu pengetahuan dan kemanusiaan serta tidak boleh melanggar hukum yang berlaku."
Most read articles by the same author(s)
- Bayu Adzikri Ramadhan, Thomas Wu, Fahriza Nurul Azizah, Analisis Preventive Maintenance Menggunakan Metode Mean Time Between Failure (MTBF) dan Mean Time to Repair (MTTR) pada Mesin Wire Rope Hoist Crane di PT Wika Beton Tbk Plant Karawang , Blend Sains Jurnal Teknik: Vol. 5 No. 1 (2026): Edisi Juli